2017 - 2019
Works at Bakun Interchange, Suai Interchange, Niah Interchange and Niah Bridge, Sarawak. Completion Date: December 31, 2019.
Origins: A chronological summary of our history and milestone from our establishment in 1996 until today.
Works at Bakun Interchange, Suai Interchange, Niah Interchange and Niah Bridge, Sarawak. Completion Date: December 31, 2019.
Road access to Empangan Baleh, Kapit Division. Contract Completion Date: May 5, 2019
Proposed Infrasturctural Works at Samalaju Industrial Park, Bintulu Division, Sarawak (Phase 3, Stage 1 – Proposed Section B1 Road) for the sum of RM81.9 million.
Bekalan Air Mukah, Bahagian Mukah, Sarawak. Completion date: November 10, 2016
500 Units-Five Floors Flats at Lot 2286, Jalan Kampung Batu Gong, Siburan, Sarawak. Completion date: December 2013
Pusa-Sesang Road, Sri Aman. Completion date ahead of schedule: August 16, 2005
SRK Long Luping, Lawas, Limbang Division, Sarawak.
Pangkalan Utama Marin Perikanan, Santubong, Kuching, Sarawak. Completion date: June 6, 2001
Sebangan Bajong Agricultural Development Project, Block B and C (Phase 1 Development), Bahagian Samarahan, Sarawak for the sum of RM18.7 million
The second restructuring of Debessa Development Sdn Bhd on April 26, 1997
The first restructuring of Debessa Development Sdn Bhd on January 15, 1997
The incorporation of Debessa Development Sdn Bhd on June 27, 1996